Back in February, Jeff Schade hung a six-foot sign on a construction tractor parked about 10 feet from Leucadia Cyclery's storefront, as a joke, and left it there. He told The Coast News that the tractor "did not start its engine for three weeks and sat in front of Avocado Street with no movement."
For most of Segment C, the construction on North Coast Highway 101 between Jupiter Street and La Costa Avenue has run down the middle of the road and underground. According to the City's most recent project update, crews are still installing water and drainage connections between Jupiter and La Costa. On the west side south of La Costa Avenue, they have started building new curb, gutter, sidewalk, bus pads and driveways. Under the City's plan, that kind of surface work comes once the underground facilities are in place, and it is the work that runs right up to the storefronts. That puts the hardest part of the project for Leucadia's small businesses at the very end, and the end is now.
Segment C's schedule has slipped more than once
Segment C started construction in 2024. It was first set to finish by summer 2025. Then the City Council added drainage work, including a new storm drain system meant to reduce flooding along the corridor, and Director of Engineering Dan Nutter told The Coast News that this pushed the timeline back by about a year and a half. In July he was aiming for October. The City's North Highway 101 project page, last updated September 17, now says "late Fall 2026." The City's Segment C FAQ, updated October 7, says construction will continue "through Fall 2026."
This segment carries an estimated $32 million price tag. The full Leucadia Streetscape runs 2.5 miles and costs more than $65 million.
What's buried, what's built, what's next
Stage | Status in the City's updates |
|---|---|
Large storm drain pipe | All 60-inch, 66-inch and 36-inch pipe installed |
Northbound lanes | Paved, with traffic on new pavement from Jupiter Street to Moorgate Road |
Roundabouts, east side | Done for "a few months" as of mid-July |
Northbound left and U-turn at La Costa Avenue | Open |
Cleanout boxes, storm drain laterals, inlets, water main | Still underway between Jupiter and La Costa |
West-side curb, gutter, sidewalk, bus pads, driveways | Underway south of La Costa Avenue |
The City's July 14 update laid out the order of work. Pipe, inlets, water main and paving would go in first along the west side. "When the underground facilities are in place," the surface work would start: sidewalks, curbs, gutters, drainage inlets and driveways. By the September update, that surface work had started on the west side south of La Costa Avenue. In the same July story, Nutter told The Coast News that sidewalk and road work would get "up close and personal" with businesses over the next few months.
Why the businesses feel it most now
Before that final phase began, the businesses along the corridor had already been dealing with construction for a long time. Stacy Reddell, executive director of the Leucadia 101 Mainstreet Association, told The Coast News that the 20 businesses she surveyed saw sales drop an average of 25% to 40% over the past year. David Shapiro, co-owner of The Leucadian, said losing street parking had discouraged customers from booking events there. Tom Chu of Leucadia Donut Shoppe said many northbound customers had to keep driving to La Costa Avenue to make a U-turn.
Sip-N-Sea shows why the sidewalk phase is so specific to each storefront. Customers order through a walk-up window on the front of the building. Owner Giuseppe Georgees told The Coast News that he wasn't sure how customers would reach the window once construction got to his storefront. When the remaining work is a new sidewalk and driveway right in front of a shop, how hard it is to get in depends on which few feet are torn up that week.
"My big concern right now is we're going to shut those businesses down for three to six months, and most of them won't make it."
Kevin Doyle, the association's treasurer and a former member of the city's Planning Commission, made that point in the same Coast News story. He also noted that the project was first proposed in 2008. Nutter said in the same story that the project was only about a month behind schedule, which he called "pretty darn good" for a construction project this size.
Several owners said they support the project and want it finished as quickly as possible. Nikolas Harth, co-owner of Surfhouse and Coffee Coffee, said his hotel has flooded in past storms, with 8 to 10 inches of water getting into a ground-floor room. He backs the drainage upgrades. The drainage work that pushed back the schedule is the part of the project meant to reduce that kind of flooding.
Getting to the shops while the work wraps up
The City says access to driveways and businesses will stay open throughout construction, and it asks the public to support Leucadia businesses while the work goes on. Here's what the City's own updates say about getting there:
- Park on the east side. In July, the City temporarily restricted curbside parking on the west side and pointed drivers to the parking pods on the east side, where road construction was finished.
- Use the La Costa turn. The northbound left and U-turn lane at La Costa Avenue is open. If a shop is on the west side and you're heading north, that's the official place to turn around.
- Watch for the new signs. Nutter told The Coast News that the City planned to add signs directing pedestrians to designated crossings and showing drivers where U-turns are allowed.
- Expect lane shifts. The City says to plan for intermittent lane shifts, noise, dust and large construction vehicles.
Some stops worth the effort on this stretch include Leucadia Cyclery at 1560 N. Coast Highway 101, Leucadia Donut Shoppe, The Leucadian, and Sip-N-Sea's walk-up window. A little farther along the 101, Coffee Coffee at 970 N. Coast Highway 101 opens at 6:30 a.m. daily, according to Surfhouse's locals guide. If you have questions about access or want project alerts, the City's outreach team is at (760) 512-3800 and [email protected].
What the finished street adds
The finished street mostly fixes the problems owners described during construction. Schade told The Coast News that the stretch between The Leucadian and Avocado Street was "pitch black" at night with no streetlights, so he put LED lighting along the eaves of his own shop. Segment C adds new streetlights. It also adds crosswalks, a pedestrian signal at Avocado Street, benches, bike racks and hundreds of new trees.
The City's FAQ fills in the rest:
- One auto lane in each direction, with roundabouts to slow traffic and cut down on stops
- A dedicated bike lane with a buffer. At the roundabouts, cyclists can either ride on the sidewalk or take the full vehicle lane
- Wider sidewalks and new crossings at the Jupiter and Grandview roundabouts and at Bishops Gate Road
- Added parking on the west side, plus median trees and irrigation
City pages don't agree on what to call the second roundabout. The FAQ calls it Grandview Street, and the project page lists it by nearby Moorgate Road. The City describes the whole corridor as a "linear park," similar to the Solana Beach Rail Trail.
After Segment C
Finishing Segment C doesn't finish the Streetscape. According to The Coast News, preliminary designs are complete for Segment B, from Basil Street to Jupiter Street, and Segment A1, from A Street to Marcheta Street, but neither has construction funding yet. Nutter also told the paper that the City plans to hold community meetings with Leucadia 101 Mainstreet through the end of the project.
No ribbon-cutting has been announced. Schade has said he hopes the City will hold a community celebration when construction ends, to help bring customers back. Until then, the businesses that have stayed open through more than two years of construction are reachable from the east-side parking pods or with a U-turn at La Costa Avenue.
The North 101 corridor is part of everyday life in Leucadia, and what happens on it shapes the neighborhood as much as any new listing. If you want to talk about how projects like the Streetscape factor into living and owning in Encinitas, Anastasia Colwell-Olsen is glad to share what she's seeing on the ground. Let's Connect.